KENTFIELD, Calif. - Californer -- Alten Construction (https://www.altenconstruction.com/), a full-service San Francisco Bay Area commercial construction company, recently wrapped up renovation work to the St. Anselm Hall on the campus of Marin Catholic High School (https://www.marincatholic.org/), an Archdiocesan, Catholic, co-ed college prep high school founded on the values of faith, knowledge and service.
St. Anselm Hall was originally designed as a convent to house the Sisters who taught at the school in the 1950s, but most recently, those rooms were turned into storage and office space. The school's recent growth spurred the restoration and St. Anselm Hall's complete revamp.
Alten Construction demolished the existing interior of the 17,733-square-foot, two-story building, reconfigured the structure with new spaces and classrooms and turned them over for student and staff occupancy in October 2020. St. Anselm Hall now consists of a new Counseling Center, Campus Ministry Center with a design made of mostly glass, three classrooms and the school's Principled Entrepreneurship Institute, an innovative curriculum where students use entrepreneurship and the discernment of their God-given gifts, talents and abilities to seek out their ultimate purpose and vocation.
More on The Californer
The commercial construction team also remodeled some existing classrooms and Poetz Theater. Other repairs included new exterior plaster and roof, a structural reboot, new lighting, plumbing, a new HVAC system and site work, overall code compliance and general building infrastructure improvements, fire sprinklers throughout St. Anselm Hall, reroofing, repainting and American's with Disabilities Act (ADA) accessibility enhancements, among others.
"I could not be happier with the completion of this game-changing project for our students and the community," said Tim Navone, president of Marin Catholic High School. "It absolutely would not have been the same without Alten Construction. Beyond the incredible quality of work and being honest and upfront at every turn, the secret sauce of Alten Construction is the trust and confidence that they are on our side and a part of our community. They approach every stage of construction as if they are building it for themselves. I look forward to working with Alten Construction again in the future."
More on The Californer
The refurbishment was divided into two phases so students were not displaced during construction. The first segment of construction included demolition of the offices while the students still occupied the theater and existing classrooms. Once school was out, the construction team stripped the entire building and reframed it. The existing and new classrooms were finished first and followed by the offices and hallways.
Located at 675 Sir Francis Drake Blvd. in Kentfield, the estimated project cost is $8.05 million. Established in 1949, the Marin Catholic student body of nearly 800 students reflects the socio-economic, cultural and ethnic diversity of the community.
St. Anselm Hall was originally designed as a convent to house the Sisters who taught at the school in the 1950s, but most recently, those rooms were turned into storage and office space. The school's recent growth spurred the restoration and St. Anselm Hall's complete revamp.
Alten Construction demolished the existing interior of the 17,733-square-foot, two-story building, reconfigured the structure with new spaces and classrooms and turned them over for student and staff occupancy in October 2020. St. Anselm Hall now consists of a new Counseling Center, Campus Ministry Center with a design made of mostly glass, three classrooms and the school's Principled Entrepreneurship Institute, an innovative curriculum where students use entrepreneurship and the discernment of their God-given gifts, talents and abilities to seek out their ultimate purpose and vocation.
More on The Californer
- Paralegal Office of Shakira A. Lasisi Expands Legal, HR, and Administrative Consulting Services from
- Lady D Releases Chiseled by Choices: Reflections on Empowerment, Growth, and Healing
- MBF Productions Launches Spring Events on the CRAFTED at the Port of L.A. Grounds in San Pedro
- Hypnotherapy Finder Announces Official US Wide Launch After Successful Soft Launch
- Ayahuasca: The Mother Of All The Plants And The Voice Of Pachamama is now available for pre-order!
The commercial construction team also remodeled some existing classrooms and Poetz Theater. Other repairs included new exterior plaster and roof, a structural reboot, new lighting, plumbing, a new HVAC system and site work, overall code compliance and general building infrastructure improvements, fire sprinklers throughout St. Anselm Hall, reroofing, repainting and American's with Disabilities Act (ADA) accessibility enhancements, among others.
"I could not be happier with the completion of this game-changing project for our students and the community," said Tim Navone, president of Marin Catholic High School. "It absolutely would not have been the same without Alten Construction. Beyond the incredible quality of work and being honest and upfront at every turn, the secret sauce of Alten Construction is the trust and confidence that they are on our side and a part of our community. They approach every stage of construction as if they are building it for themselves. I look forward to working with Alten Construction again in the future."
More on The Californer
- Melzi Job Coach Launches on iOS and Android: A Privacy-First AI Career Engine Built for Execution
- "The Mystery of Emma Thorn" Earns Nomination & Official Selection of the New Media Film Festival
- Fresh Lifelines for Youth Appoints Laksmi Lagares as Vice President of Development
- RAW Marketing Agency Expands Nationwide Serving Small Businesses in Los Angeles, Miami and New York
- California: Governor Newsom highlights mental health resources for veterans as Middle East conflict continues
The refurbishment was divided into two phases so students were not displaced during construction. The first segment of construction included demolition of the offices while the students still occupied the theater and existing classrooms. Once school was out, the construction team stripped the entire building and reframed it. The existing and new classrooms were finished first and followed by the offices and hallways.
Located at 675 Sir Francis Drake Blvd. in Kentfield, the estimated project cost is $8.05 million. Established in 1949, the Marin Catholic student body of nearly 800 students reflects the socio-economic, cultural and ethnic diversity of the community.
Source: Alten Construction
Filed Under: Construction
0 Comments
Latest on The Californer
- San Diego's Leading Digital Marketing Agency California Web Coders Helps Businesses Achieve Online G
- California: Governor Newsom announces more than $23 million to increase access to farm-fresh food for CalFresh, WIC, and Senior Farmers' Market Nutrition Program recipients
- Professional San Diego Web Design Service Custom Website Solution: California Web Coders Helps Busi
- Digital Marketing & Web Experts CA: California Web Coders Helps Businesses Grow Online in 2026
- UCLA Black Alumni Association Hosts 2026 Winston C. Doby Legacy Scholarship Gala
- Top Rated San Diego Web Design Agency: California Web Coders Driving Digital Growth for Businesses
- MVP to Showcase AI-Driven Inspection for SMT, Packaging, and Microelectronics at APEX EXPO 2026
- $317M Revenue and a Clear Path to $1B: $IQST is Positioned for a Major Profitability Inflection
- ASI Hosts 2026 Executive Business Summit for Global Partner Community
- Statement of Compassion from Honorable Pamela Price on Mass Shooting March 7, 2026 in Oakland, CA
- Pastor Saeed Abedini Releases THE TRUTH – Volume 1, A Deeply Personal Story of Faith, Struggle, and Redemption
- New Book Warring From the Standpoint of the Throne Room Calls Believers to Pray From Victory
- Gift Ideas That Look Luxurious and Always Feel Special
- Community Leaders Gather in Corona for Dialogue & Friendship Iftar During Ramadan
- Reggae on the River Announces Phase 2 Lineup for 2026 Festival
- Scotch Whisky Market Dislocation Creates Compelling Entry Opportunity for Long-Term Investors
- SEEAG's 13th Annual Ventura County Farm Day
- Peccioli Becomes New Orleans: In July 2026, the magic of jazz comes to Tuscany
- Wordly Enhances Live Subtitles & Captions Featureto Meet Global Demand
- H Mart to Open New Dublin Store on March 26, 2026