KENTFIELD, Calif. - Californer -- Alten Construction (https://www.altenconstruction.com/), a full-service San Francisco Bay Area commercial construction company, recently wrapped up renovation work to the St. Anselm Hall on the campus of Marin Catholic High School (https://www.marincatholic.org/), an Archdiocesan, Catholic, co-ed college prep high school founded on the values of faith, knowledge and service.
St. Anselm Hall was originally designed as a convent to house the Sisters who taught at the school in the 1950s, but most recently, those rooms were turned into storage and office space. The school's recent growth spurred the restoration and St. Anselm Hall's complete revamp.
Alten Construction demolished the existing interior of the 17,733-square-foot, two-story building, reconfigured the structure with new spaces and classrooms and turned them over for student and staff occupancy in October 2020. St. Anselm Hall now consists of a new Counseling Center, Campus Ministry Center with a design made of mostly glass, three classrooms and the school's Principled Entrepreneurship Institute, an innovative curriculum where students use entrepreneurship and the discernment of their God-given gifts, talents and abilities to seek out their ultimate purpose and vocation.
More on The Californer
The commercial construction team also remodeled some existing classrooms and Poetz Theater. Other repairs included new exterior plaster and roof, a structural reboot, new lighting, plumbing, a new HVAC system and site work, overall code compliance and general building infrastructure improvements, fire sprinklers throughout St. Anselm Hall, reroofing, repainting and American's with Disabilities Act (ADA) accessibility enhancements, among others.
"I could not be happier with the completion of this game-changing project for our students and the community," said Tim Navone, president of Marin Catholic High School. "It absolutely would not have been the same without Alten Construction. Beyond the incredible quality of work and being honest and upfront at every turn, the secret sauce of Alten Construction is the trust and confidence that they are on our side and a part of our community. They approach every stage of construction as if they are building it for themselves. I look forward to working with Alten Construction again in the future."
More on The Californer
The refurbishment was divided into two phases so students were not displaced during construction. The first segment of construction included demolition of the offices while the students still occupied the theater and existing classrooms. Once school was out, the construction team stripped the entire building and reframed it. The existing and new classrooms were finished first and followed by the offices and hallways.
Located at 675 Sir Francis Drake Blvd. in Kentfield, the estimated project cost is $8.05 million. Established in 1949, the Marin Catholic student body of nearly 800 students reflects the socio-economic, cultural and ethnic diversity of the community.
St. Anselm Hall was originally designed as a convent to house the Sisters who taught at the school in the 1950s, but most recently, those rooms were turned into storage and office space. The school's recent growth spurred the restoration and St. Anselm Hall's complete revamp.
Alten Construction demolished the existing interior of the 17,733-square-foot, two-story building, reconfigured the structure with new spaces and classrooms and turned them over for student and staff occupancy in October 2020. St. Anselm Hall now consists of a new Counseling Center, Campus Ministry Center with a design made of mostly glass, three classrooms and the school's Principled Entrepreneurship Institute, an innovative curriculum where students use entrepreneurship and the discernment of their God-given gifts, talents and abilities to seek out their ultimate purpose and vocation.
More on The Californer
- 10xLaw.com Extends Employment Opportunity to Kim Kardashian
- DecisionPoint Technologies Accelerates Growth with Acquisition of Acuity Technologies
- CCHR: Involuntary Commitment Is Eugenics Repackaged as "Mental Health Care"
- Pacsun Announces Industry First Pacsun Youth Advisory Council: Empowering Its Consumers as Co-Creators in Brand Strategy
- Q2 2025 Industry Impact Report Underscores Semiconductor Expansion, Talent Development and Sustainability Milestones
The commercial construction team also remodeled some existing classrooms and Poetz Theater. Other repairs included new exterior plaster and roof, a structural reboot, new lighting, plumbing, a new HVAC system and site work, overall code compliance and general building infrastructure improvements, fire sprinklers throughout St. Anselm Hall, reroofing, repainting and American's with Disabilities Act (ADA) accessibility enhancements, among others.
"I could not be happier with the completion of this game-changing project for our students and the community," said Tim Navone, president of Marin Catholic High School. "It absolutely would not have been the same without Alten Construction. Beyond the incredible quality of work and being honest and upfront at every turn, the secret sauce of Alten Construction is the trust and confidence that they are on our side and a part of our community. They approach every stage of construction as if they are building it for themselves. I look forward to working with Alten Construction again in the future."
More on The Californer
- 84 Ethiopian Churches Change Signboards to Shincheonji Church of Jesus
- BTXSGG Outlines Four-Pillar Framework to Enhance Digital Asset Security and Compliance
- NJTRX Positions for Next-Generation Asset Trading with U.S. Regulatory Framework
- America's SBDC Announces 2025-2026 Board of Directors
- Avoid Swirl Marks When You Get a Car Wash in Downey CA
The refurbishment was divided into two phases so students were not displaced during construction. The first segment of construction included demolition of the offices while the students still occupied the theater and existing classrooms. Once school was out, the construction team stripped the entire building and reframed it. The existing and new classrooms were finished first and followed by the offices and hallways.
Located at 675 Sir Francis Drake Blvd. in Kentfield, the estimated project cost is $8.05 million. Established in 1949, the Marin Catholic student body of nearly 800 students reflects the socio-economic, cultural and ethnic diversity of the community.
Source: Alten Construction
Filed Under: Construction
0 Comments
Latest on The Californer
- California claims victory – again – over Huntington Beach as appeals court rules against city's NIMBY violations of state law
- The Great Junk Hunt Returns to Roseville – A Vintage Shopping Adventure Awaits!
- Erdos Technologies CEO Dan Herbatschek Emphasizes the Importance of Software in Helping Companies Make More Intelligent Decisions on Inventory Flow and Management
- MyNamePlayer Empowers Educators to Create Inclusive Classrooms Through Correct Name Pronunciation
- Long Beach Seeks Volunteers for 41st Annual California Coastal Cleanup Day, September 20
- Youth Take the Lead: Kopp Foundation for Diabetes Hosts "By Youth, For Youth, With T1D" Gala on October 8 at Blue Bell Country Club
- Wise Business Plans Launches Business Plan Writing Services in San Diego to Propel Entrepreneurs
- Green Office Partner Named #1 Best Place to Work in Chicago by Crain's for 2025
- Apex Raises $200 Million Series D Financing
- CCHR, a Mental Health Watchdog Organization, Hosts Weekly Events Educating Citizens on Important Mental Health Issues
- "Leading From Day One: The Essential Guide for New Supervisors" Draws from 25+ Years of International Management Experience
- New Slotozilla Project Explores What Happens When the World Goes Silent
- Long Beach City Council Adopts Fiscal Year 2026 Budget
- Lights, Camera, Action Underway as The 23rd Oakland International Film Festival Shines Spotlight on Justice, Healing & Community
- California: Governor Newsom announces appointments 9.11.25
- The Two Faces of Charles D. Braun: How the Novel, Posthumously Yours, Came to Life
- Eastwood Ranch Foundation Hosts Annual Benefit 'Wags & Wishes' on 9/20
- Singer-Songwriter Ben Kaplan is Ready to Share His Intimate Music with the World
- California: Governor Newsom honors fallen State Correctional Officer Townsend
- Author Tells Why Trump is the Worst Profiteering US President in History